Logotipo ISASTUR
Safety Manual. Revised Edition 2010

Revised Edition 2010

Risk Assessment: Construction and Civil Works

Workers Affected by Works Hazards

The levels of risk shown above help us to decide whether we should adopt measures of control, with what degree of urgency and what the extent of the economic effort should be:

RISK ACTION AND TIMING
Trivial
(T)
Although specific actions may not be necessary, not very costly preventive measures are to be considered to avoid aggravating the hazard.
Tolerable
(To)
The preventive action does not need to be improved; however, more cost-effective solutions should be considered or improvements that do not suppose a substantial economic burden.
Periodic checks are needed to ensure that the efficacy of control measures is maintained.
Moderate
(Mo)
Efforts should be made to reduce the hazard, determining the investments needed. Measurements to reduce the hazard should be implanted within a certain period of time.
When the moderate risk is associated with extremely harmful consequences, measures are to be established to control said risk (to be defined in the action plan ).
Important
(I)
Work should not commence until the hazard has been reduced.
Considerable resources may be needed to control the risk.
When the risk corresponds to a job that is being carried out, the problem must be remedied in less time than that of moderate risks.
Intolerable
(In)
Work should not commence or continue until the risk has been reduced. If it is not possible to reduce the risk, even with unlimited resources, the work must be prohibited.
This situation is equivalent to exposure to a serious or imminent risk.

Finally, the factors that can cause each of the assessed risks are discussed in detail, as well as the planned preventive and protective measures to control these risks. However, it should be noted that this Risk Assessment is general in nature and that the description and exhaustive assessment of the different risk which workers may find themselves exposed to are included in the corresponding Health and Safety Plan of the job in question.

JOB / AREA
1.1.1. CONSTRUCTION AND CIVIL WORKS WORKER
Code Identified risk Likelihood Seriousness Estimation
L M H SD H EH T To Mo I In
-- Traffic accidents in transit X         X     X    
10 Persons falling onto a different level X         X     X    
20 Persons falling onto the same level X     X       X      
30 Objects falling (40) (50)   X     X       X    
60 Stepping on objects X     X     X        
70 Knocking against or being hit by objects (80) X       X     X      
90 Blows/cuts caused by objects or tools   X     X       X    
100 Projected particles   X     X       X    
110 Becoming trapped by or between objects X         X     X    
120 Becoming trapped due to machines overturning X         X     X    
230 Being run over or hit by vehicles X         X     X    
-- Flooding X     X     X        
150 Thermal Contacts X         X     X    
161 Electrical Contacts (162) X         X     X    
130 Overstrain   X     X       X    
140 Exposure extreme ambient T X     X     X        
170 Exposure to noxious or toxic substances X       X     X      
211 Fire (212) (213)   X     X       X    
200 Explosions X         X     X    
310 Exposure chem. pollutants   X     X       X    
330 Exposure to noise   X     X       X    
340 Exposure to vibrations X       X     X      
370 Exposure to non-ionizing radiation X       X     X      
420 Physical fatigue (430) (440)   X     X       X    
410 Visual fatigue   X     X       X    

Copyright © 2010 ISASTUR